Click the links below to view Highway 53 construction updates:
August 1, 2025
Work completed in the last week includes:
- Curb removals;
- Roadwork on 54 Street related to the road closure;
- Installation of pre-cast bases for new lighting along the corridor;
- Catch basins installed along the corridor;
- Saw cuts and curb removals for concrete repairs; and
- A new hydrant installed on 54 Street.
Work anticipated over the next week:
- Base work and road construction on 54 Street related to the road closure;
- Electrical drilling to install power cables for new lighting along the corridor; and
- Concrete installation throughout the corridor including curbs and entrances.
August 7, 2025
Work completed in the last week includes:
- Electrical work for streetlighting, including base installation, conduit and electrical drilling;
- Curbs poured at 54 Street and throughout the Highway 53 corridor; and
- Islands at 45 Avenue Crescent poured and completed.
Work anticipated over the next week:
- Continued concrete installation throughout the roadway;
- Continued electrical work for streetlights, and trenching to begin for tree lighting; and
- Safeguarding of existing trees in preparation for road construction.
August 14, 2025
Work completed in the last week includes:
- Base work for streetlights and trenching for power;
- Continued concrete work on curbs, gutters and wheelchair ramps; and
- Pedestrian flashers were installed at 45 Avenue Crescent.
Work anticipated over the next week:
- Continued electrical work and trenching for power;
- Continued base work and installation of street lights; and
- Continued concrete installation throughout the roadway.